Change Order Calculator

"While you're here, can you also..." — Change orders are profit killers when priced wrong (or not priced at all). Calculate the true cost of extra work and price it to protect your margin.

How It Works

Enter the additional materials, labor hours, and any delay/disruption costs. Add your standard overhead and profit margin. The calculator gives you a change order price that maintains profitability — not just covers costs.

Example: "Can You Add a Ceiling Fan?"

Materials: $200. Labor: 3 hrs × $45 = 35. Trip charge/disruption: $75. Cost: $410. At 20% margin: $513 change order. Most contractors would say "$300" off the top of their head — leaving $213 on the table and teaching the customer that extras are cheap.

Frequently Asked Questions

Should I charge overhead on change orders?

Yes. Your overhead doesn't pause because it's "just a small extra." The truck, insurance, and office still cost money during change order work.

What if the customer balks at the price?

That's information. If they won't pay a fair price for extra work, they were never going to be a profitable customer. Better to know now.

Do I need a written change order?

Absolutely. Verbal agreements on extra work are the #1 source of payment disputes. Price it, write it, sign it, then do the work.

Related Calculators

Job Profit | What to Charge | Crew Cost

Blue Collar Banker

Run the numbers
before the bank does.

Sixteen plain-talk calculators for owners in the trades — built by a business banker, written in shop language. No jargon, no sales pitch. Just the math the way an underwriter sees it.

CAN YOUR BUSINESS AFFORD THE LOAN?

Underwriters live on one ratio: DSCR — your cash flow divided by everything you owe each year. Most banks want 1.25× or better. That means for every $1.00 of loan payments, you need $1.25 of cash flow. Run yours before you ever sit down across the desk.

Your numbers

Use last year's tax return or year-to-date financials. Rough is fine — this is a first look, not an application.

Cash flow available to pay debt (per year)

$
$
$
$

What you owe (per year)

$
$

Your DSCR

Cash flow ÷ total yearly debt payments

—
Cash flow available: —
Total debt payments / yr
—
DSCR on today's debts only
—
Max payments a bank likes at 1.25×
—
Room left for new payments
—

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: ratios like this one, equipment math, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Finance it, lease it, or pay cash?

Same machine, three very different price tags. Compare the total cost of each path — not just the monthly payment — and see how much cash each one leaves in your operating account the day you sign.

The equipment

Start with the machine. Then set the terms you're being quoted for each option.

$
%

If you finance it

%
%
mo

If you lease it

$
mo
$
$

Your cash's other job

%

Total cost, side by side

Total dollars out over the term, including tax, interest, fees, and buyout.

Finance—
—
Lease—
—
Pay cash—
—
Finance payment
—
Cash to close — finance
—
Cash to close — lease
—
Cash to close — cash deal
—

Cost isn't the whole story. Financing and leasing keep cash in the business for payroll and slow months; paying cash owns the machine free and clear with zero payments hanging over a bad quarter. Tax treatment differs too — that's a CPA conversation, and it's worth having before you sign.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: equipment decisions like this one, loan ratios, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

How long could you run on empty?

If the phone stopped ringing tomorrow, how many months could your cash carry payroll, rent, and the notes? That's your runway — and it's the number that decides whether a slow season is an inconvenience or an emergency.

Your numbers

Monthly figures. Use a normal month, not your best one.

$
$

Money out, per month

$
$
$
$

Stress-test it

In a downturn, job costs fall with the work — but payroll, rent, and payments don't. The stress test cuts revenue and job costs, and holds the rest flat.

Your runway

In a normal month

—
—
Net cash per month
—
Total out per month
—
3-month cushion target
—
Gap to a 3-month cushion
—

The cushion target is three months of the bills you can't pause — payroll, rent, insurance, and debt payments. Job costs aren't in it, because when work stops, they mostly stop too.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: cash flow and runway, loan ratios, and equipment math, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Did I actually make money on that job?

The check cleared — but did the job actually pay you? Add up everything the job really cost: materials, labor, equipment, and the odds and ends that never make it onto the invoice. What's left is your true profit, and the margin tells you whether you'd take the same job again.

Your numbers

One finished job. Use what it actually cost — not what you estimated when you bid it.

$
$
$
$
$

What the job really made

What the customer paid, minus every cost the job carried.

—
True profit on this job
Total job costs
—
Profit margin
—

Margin is profit as a share of the price — it's the number that decides whether a job was worth the risk, the trucks, and the weekends. Busy is not the same as profitable.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: job profit math like this one, pricing, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What should I charge for this job?

Most owners price a job by adding up the costs and tacking on a little. This works the other way: start with the profit margin you want to keep, and let the math set the price. Quote below the break-even number and you're paying to work.

Your numbers

Your best estimate of what the job will cost — then the margin you want left over when it's done.

$
$
$
%

Your quote

Costs, plus the margin you chose — priced before you start, not hoped for after.

—
Suggested quote
Total estimated costs
—
Break-even price
—
Profit at suggested quote
—

Margin is not markup. A 20% margin on a $26,250 quote leaves $5,250 — adding 20% on top of costs instead would leave you short. This math divides by (1 − margin) so the percentage you want is the percentage you actually keep.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: pricing math like this one, job profit, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What does my crew really cost?

The wage on the paycheck is only part of what an hour of labor costs you. Payroll taxes, workers' comp, and benefits ride on top — and only some of the hours you pay for ever get billed to a job. The number at the end is the one your prices have to beat.

Your numbers

One typical crew member. Taxes and comp are percentages of the wage — check your last payroll report or comp policy if you're not sure.

$
%
%
$
%

The real cost of an hour

Loaded cost, and what each billed hour actually has to cover.

—
True cost per billable hour
Loaded hourly cost
—
Annual cost per full-time employee
—

Drive time, rain days, shop time, and callbacks all get paid — they just don't get billed. The fewer of your paid hours land on a job, the more each billed hour has to carry.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: labor cost math like this one, pricing, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

How much must I sell to break even?

Rent, insurance, office salaries — the bills that show up whether you sell anything or not. This shows the sales you need every month just to cover them, before a dime of profit. Everything above this line is yours; everything below it comes out of your pocket.

Your numbers

Two numbers: what it costs to keep the doors open each month, and how much of every sales dollar your jobs eat.

$
%

Your break-even line

Sales needed to cover fixed expenses at your job-cost percentage.

—
Break-even sales per month
Weekly break-even
—
Daily break-even
—

Daily is the monthly number spread over 22 working days. Watch what happens when the job-cost percentage creeps up a few points — the break-even line moves fast, and it moves against you.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: break-even math like this one, cash flow, and loan ratios, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Will I have enough cash to make payroll?

Profit on paper doesn't make payroll — cash in the bank does. Line up what you have, what's coming in, and what's going out, week by week for a full quarter. If there's a short week coming, you want to see it now, not on payday.

Your numbers

Weekly averages are fine — this is an early-warning system, not an audit.

$
$
$
$

13 weeks of cash

Ending balance each week, at your current pace.

—
Net cash per week — payments in, bills and payroll out
Lowest cash point
—
Lowest week
—
Cash at week 13
—
First short week
—

Week by week

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: cash planning like this one, runway, and loan ratios, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What does my excavator cost per hour?

A machine costs money every hour it runs — whether the invoice shows it or not. Depreciation, insurance, fuel, and repairs all ride along on every job. Know your true hourly cost and you know the floor your equipment rate can never go below.

Your numbers

One machine. What you paid for it, how long it'll last, and what it burns to run.

$
hrs
$
$
$
hrs

True cost per hour

Every cost the machine carries, spread over the hours it actually works.

—
Total cost per operating hour
Depreciation / hr
—
Insurance / hr
—
Operating / hr (fuel + repairs)
—

Depreciation is real money even though no bill arrives for it — the machine is worth less every hour it runs, and one day it has to be replaced. If your rate doesn't cover this number, you're slowly selling the machine to your customers at a loss.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: equipment cost math like this one, pricing, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Can I afford to hire another person?

The salary is never the real cost. Payroll taxes, workers' comp, and benefits ride on top — figure roughly a third more before the new hire turns a wrench. This shows the true monthly cost next to the new revenue they have to bring in to pay for themselves.

Your numbers

The offer you're thinking about — and the work this person would actually generate.

$
%
$

The true monthly cost

Salary plus burden — what this hire actually takes out of the account every month.

—
True cost per month, all-in
New revenue / mo
—
Monthly surplus
—
True cost / yr
—

Be honest about the revenue number — a new hire takes weeks to get up to speed, and the revenue only counts if there's sold work waiting for them. Hiring ahead of demand is how good shops get cash-poor.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: hiring math like this one, labor costs, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What does cutting my price really cost?

A 10% discount sounds small. But the discount comes straight out of your profit — not out of your costs — so the hole is far bigger than it looks. This shows how many extra jobs you'd have to win just to make the same money you make now.

Your numbers

A typical job, your real margin on it, and the discount on the table.

$
%
%

What the discount really does

Same job, same costs — the discount comes out of the profit line only.

—
New discounted price per job
Profit per job — before
—
Profit per job — after
—
Extra jobs needed
—
That's winning
—

The math is brutal because your costs don't drop with your price — materials, labor, and fuel still cost what they cost. The thinner your margin, the more extra volume a discount demands.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: pricing math like this one, margins, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

How long can I last through a slow season?

Slow seasons don't kill shops overnight — they drain the account a little every month until the wall shows up. This takes your cash, your fixed costs, and your slow-season revenue and tells you exactly when that wall is.

Your numbers

Fixed costs are the bills that arrive whether work does or not.

$
$
$

Your slow-season runway

How long the cash carries the fixed bills at slow-season revenue.

—
Months of survival at this pace
Monthly cash burn
—
The cash wall hits
—

Knowing the wall's date changes the conversation — you can line up work, trim costs, or talk to your banker while you still have months of cash behind you, instead of days.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: cash planning like this one, runway, and loan ratios, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What should I charge for that change order?

"While you're at it…" is where job profit goes to die. Every change has a real cost — materials, labor hours, equipment — and if you don't price it with markup before the work starts, you just donated it. Run the change through here first.

Your numbers

Just the change — not the original job. Everything the extra work actually adds.

$
hrs
$
$
%

Your change-order price

True cost of the change, plus your markup — agreed before the work starts.

—
Suggested change-order price
True cost of the change
—
Your profit on the change
—

Get it in writing before the work starts — a signed change order is a receivable, a handshake is a donation. The markup isn't greed; it covers the scheduling disruption and the risk every change carries.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: change-order math like this one, job profit, and pricing, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Is each truck making money?

A busy truck isn't always a profitable truck. Add up everything one truck or crew carries for a month — payment, fuel, maintenance, wages — and set it against what that truck actually billed. The margin tells you whether it's a business or just a job with a payment book.

Your numbers

One truck, one month. Revenue it generated and every cost it carried.

$
$
$
$
$
$

What the truck really earns

Revenue minus every cost the truck carries, for one month.

—
Monthly profit from this truck
Total monthly costs
—
Profit margin
—
Profit per working day
—

Run every truck through this. The fleet average hides the loser — and one truck bleeding a few hundred a month quietly eats what the best truck earns.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: truck and crew math like this one, job profit, and cash flow, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

How much cash does growing eat?

Growth spends cash before it makes cash. Bigger sales mean bigger material orders, bigger payroll weeks, and more money floating in receivables — all before the new work pays you back. This shows how much cash the growth run ties up, so you can line it up first.

Your numbers

Where sales are now, where you want them, and what your jobs cost to run.

$
%
%
mo

The cash the growth run needs

Extra job costs you'll front every month at the new sales level.

—
Total cash needed to fund the growth run
New monthly sales target
—
Extra cash tied up / mo
—

This is the number behind "we're growing and we're broke." The work is profitable — the cash is just stuck in materials, payroll, and receivables. A line of credit sized before the growth starts is what separates a ramp from a wreck.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: growth math like this one, cash flow, and loan ratios, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

What does waiting to get paid cost me?

When a customer pays in 90 days instead of 30, they're borrowing from you — at your cost of money, not theirs. If you're carrying a line of credit while they sit on your invoice, this is the interest you're paying for the privilege of waiting.

Your numbers

The invoice that's aging, and what your money costs you.

$
%

The cost of waiting

Interest you're effectively fronting while the invoice ages.

—
Cost of waiting 90 days
Waiting 30 days
—
Waiting 60 days
—
Waiting 90 days
—

Multiply this across every slow-paying customer and the number gets real fast. Net-30 terms with early-pay discounts — or deposits up front — aren't paperwork. They're profit protection.

Join the Blue Collar Banker email list

Join the weekly email and take your numbers with you — save a clean one-pager for your banker or CPA. One plain-talk money lesson for owners every week: receivables math like this one, cash flow, and pricing, all in shop language.

EMAIL ME MY RESULTS

Get a copy of your numbers to save, review, or share with your banker or CPA.

Prints just your numbers on one clean page — choose “Save as PDF” in the print dialog.

Blue Collar Banker

You're on the list.

Your personalized one-pager is on its way to .

Your one-pager

Sending your one-pager…

Prints just your numbers — choose "Save as PDF" in the print dialog.

Back to the calculators